Early Start and Early Finish Dates
In Critical Path Method (CPM), the early start (ES) and early finish (EF) dates concept is crucial. It represents the earliest start and end times for each project activity, assuming everything prior was completed as soon as possible. ES is calculated from the project start towards the finish, and …
CAPM - Early Start and Early Finish Dates Example Questions
Test your knowledge of Early Start and Early Finish Dates
Question 1
In a project with tasks A (4 days), B (3 days), and C (5 days), where B can start after A finishes and C after B, if the project begins on March 1st, what's the Early Start date for task C?
Question 2
In a construction project, the Early Start date for a critical task is identified as Day 5. If the duration of the task is 10 days, what is the Early Finish date for this task?
Question 3
In a project with tasks S (3 days), T (6 days), and U (4 days), where T can start only after S finishes and U after T, if the project begins on April 1st, what's the Early Start date for task U?