Forward Pass
Forward pass is a technique used to estimate the early start and early finish dates for the uncompleted portions of all network activities. This is done by moving forward through the project's network diagram, with the objective of identifying the project timeline. It's an important concept in unde…
CAPM - Forward Pass Example Questions
Test your knowledge of Forward Pass
Question 1
You are working on a project where the activity has an earliest start time (EST) of 5 days and a latest start time (LST) of 10 days. What is the total float of this activity?
Question 2
You are managing a project with an activity that has an earliest start time (EST) of 4 days and a duration of 6 days. What would be the earliest finish time (EFT) for this activity in a forward pass calculation?
Question 3
Assume you manage a project and the Final activity is planned to finish on the 30th day (EFT). The activity has a duration of 10 days. What's the earliest start time (EST) in a forward pass calculation?