Late Start and Late Finish Dates
Late Start (LS) and Late Finish (LF) dates indicate the latest possible times an activity can start and finish without delaying the overall project, respectively. Computed from the project end towards the start, they provide a deadline for each task. By comparing the LS and LF with the ES and EF, p…
CAPM - Late Start and Late Finish Dates Example Questions
Test your knowledge of Late Start and Late Finish Dates
Question 1
In a project, the late start of a critical path task is April 1st and the late finish is April 14th. However, the actual start was on March 20th. What does this mean?
Question 2
In a automation system upgrade project, due to a last minute design change, a critical task which originally had late start and late finish dates of March 20 and April 10 respectively, now starts on April 1. What would this indicate?
Question 3
In a project management software, the late start date for a task is set to October 1, and the late finish date is October 15. The project team begins the task on September 25. What does this situation most likely indicate?