Project Duration
Project duration is the time between the start and the completion of the project. It is a crucial element of the Critical Path Method. This method aims at determining the shortest possible project duration by optimizing the sequence of tasks. It does so by highlighting activities that directly impa…
CAPM - Project Duration Example Questions
Test your knowledge of Project Duration
Question 1
Your project has a total duration of 9 months. Due to a business requirement, stakeholders are asking to complete the project in 7 months without any additional budget. What would be your approach?
Question 2
You are managing a project with a total duration of 12 months. However, your stakeholders express a sudden desire for the project to be completed in 10 months without expanding the budget or altering delivery standards. What should you do?
Question 3
Which project estimation technique uses optimistic, pessimistic, and most likely estimates to calculate expected activity durations?