Project Network Diagrams

5 minutes 5 Questions

Project Network Diagrams are a type of flow chart and are primary tools for displaying the sequence of activities in a project. The main types of network diagrams used in project management are the PERT and Gantt charts. These visuals help to establish the timeline, identify dependencies, and pinpo…

Test mode:
CAPM - Project Network Diagrams Example Questions

Test your knowledge of Project Network Diagrams

Question 1

You are working on a project with three tasks: P, Q, and R. Q can only start when both P and R have completed. Task P takes 8 days, Task Q takes 5 days, and Task R takes 9 days. How would this be represented in the project network diagram?

Question 2

Your team is developing a software program. In the project network diagram, there's an activity H which doesn't depend on any other activity. How should this be represented in the diagram?

Question 3

In a project network diagram, what does a 'merge point' represent?