Earned Value (EV)
Earned Value, also known as Budgeted Cost of Work Performed (BCWP), measures the actual performance of the project. Essentially, it is the value of the work that has actually been done expressed in terms of the approved budget allocated for that work. By comparing the EV to PV, we can determine whe…
CAPM - Earned Value (EV) Example Questions
Test your knowledge of Earned Value (EV)
Question 1
Your organisation has entrusted you with a research project worth $1,000,000. In the first two months, you manage to complete only 20% of the project with an expenditure of $300,000. What is the Earned Value (EV)?
Question 2
Scenario: You are handling a construction project with a budget at completion (BAC) of $500,000. At the end of month three, you calculate that you have completed 40% of the project. What is the Earned Value (EV)?
Question 3
Scenario: A project with a total cost of $2,000,000 is underway. You have spent $1,000,000 so far and have completed 60% of the work. What is the Earned Value (EV)?