Earned Value (EV)
Earned Value, also known as Budgeted Cost of Work Performed (BCWP), measures the actual performance of the project. Essentially, it is the value of the work that has actually been done expressed in terms of the approved budget allocated for that work. By comparing the EV to PV, we can determine whether we are ahead or behind our planned schedule. Conversely, by comparing EV to AC, we can judge whether we are under or over our planned budget.
Guide: Understanding and Answering Questions on Earned Value (EV)
Earned Value (EV) is a crucial concept to grasp in the field of project management. It reflects the actual value accomplished from the work executed.
Why It's Important:
Understanding EV is essential because it provides an objective evaluation of the current project status, enabling efficient cost and schedule management. It also serves as an excellent tool to forecast future project performance.
How It Works:
The calculation of EV relies on two particular components - the Baseline Plan (BP) and the Actual Work Accomplished. It is the budgeted cost of the work that has been truly completed during a specific period and is typically calculated as:
EV = % of completed work x Budget at Completion (BAC)
Exam Tips: Answering Questions on Earned Value (EV)
Step 1: Identify and understand the question related to EV deeply. It could either ask for the actual value calculation or using EV for estimating at completion.
Step 2: For EV calculations, ensure to have a sound understanding of the relationship between EV, BAC and percent completion of work.
Step 3: If the question asks for further calculations based on EV, like cost performance (CPI) or schedule performance (SPI), remember to use the respective formulas. The key is to understand the interdependence of these values.
Step 4: Practice numerical problems involving EV calculations regularly for a better understanding.
Step 5: In theoretical questions or case studies, remember to highlight the comprehensive insights rendered by EV about project's cost and schedule status.
In the end, it's all about understanding the underlying principles of EV and how it links the project's schedule, scope and cost management.
CAPM - Earned Value Management Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
Scenario: You are handling a construction project with a budget at completion (BAC) of $500,000. At the end of month three, you calculate that you have completed 40% of the project. What is the Earned Value (EV)?
Question 2
Your organisation has entrusted you with a research project worth $1,000,000. In the first two months, you manage to complete only 20% of the project with an expenditure of $300,000. What is the Earned Value (EV)?
Question 3
Scenario: A project with a total cost of $2,000,000 is underway. You have spent $1,000,000 so far and have completed 60% of the work. What is the Earned Value (EV)?
Go Premium
Certified Associate in Project Management Preparation Package (2024)
- Earn 15 PDUs needed for your CAPM certification
- 4454 Superior-grade Certified Associate in Project Management practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless CAPM preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!