Estimate at Completion (EAC)

5 minutes 5 Questions

Estimate at Completion (EAC) represents the forecasted value of costs at the end of the project. It provides an estimate of what the project is expected to cost. Normally, this estimate is a combination of the money already spent (actual costs) and the estimate to complete (the remaining work). Thi…

Test mode:
CAPM - Estimate at Completion (EAC) Example Questions

Test your knowledge of Estimate at Completion (EAC)

Question 1

In a project where the Budget at Completion (BAC) is $600,000, the Actual Cost (AC) is $250,000, and the Earned Value (EV) is $200,000, which formula should be used to calculate the Estimate at Completion (EAC) if we assume future cost performance will improve?

Question 2

You're working on a project with a BAC of $120,000 and a CPI of 1. If the project progress continues at this performance, what would be the project's EAC?

Question 3

In a project where the BAC is $400,000, AC is $150,000, and EV is $120,000, which formula best represents the Estimate at Completion (EAC) assuming the current cost variance will persist?

More Estimate at Completion (EAC) questions
34 questions (total)