Schedule Performance Index (SPI)

5 minutes 5 Questions

The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as a ratio of earned value to planned value. If a project's SPI is less than 1.0, it means the project is behind schedule. Conversely, an SPI of greater than 1.0 indicates the project is ahead of schedule. The SPI f…

Test mode:
CAPM - Schedule Performance Index (SPI) Example Questions

Test your knowledge of Schedule Performance Index (SPI)

Question 1

A company is completing an energy efficiency project. The EV is $10,000, PV is $8,000, and AC is $9,000. However, the energy savings are less than predicted. How might they improve the SPI?

Question 2

A tech company has an EV of $18,000, AC of $15,000, and PV of $22,000 in its big data project. The SPI is less than one. What if the company finishes its project today, a week earlier than planned?

Question 3

In the middle of an e-commerce project, the SPI dipped from 1.2 to 0.9. What should be the project manager's main attention area?

More Schedule Performance Index (SPI) questions
45 questions (total)