Schedule Performance Index (SPI)
The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as a ratio of earned value to planned value. If a project's SPI is less than 1.0, it means the project is behind schedule. Conversely, an SPI of greater than 1.0 indicates the project is ahead of schedule. The SPI f…
CAPM - Schedule Performance Index (SPI) Example Questions
Test your knowledge of Schedule Performance Index (SPI)
Question 1
A company is completing an energy efficiency project. The EV is $10,000, PV is $8,000, and AC is $9,000. However, the energy savings are less than predicted. How might they improve the SPI?
Question 2
A tech company has an EV of $18,000, AC of $15,000, and PV of $22,000 in its big data project. The SPI is less than one. What if the company finishes its project today, a week earlier than planned?
Question 3
In the middle of an e-commerce project, the SPI dipped from 1.2 to 0.9. What should be the project manager's main attention area?