Schedule Variance (SV)
Schedule variance is a measure of schedule performance on a project. It is the algebraic difference between the earned value (EV) and the planned value (PV). SV = EV - PV. It helps determine if the project is ahead of schedule (SV > 0) or behind schedule (SV < 0). A positive schedule variance means…
CAPM - Schedule Variance (SV) Example Questions
Test your knowledge of Schedule Variance (SV)
Question 1
In a digital marketing project, the team has spent $21000 out of the $15000 budgeted, and the value of work done so far is calculated as $19000. How would the Schedule Variance look?
Question 2
Project A had an Earned Value (EV) of $30000 and a Planned Value (PV) of $35000, but the Actual Cost (AC) amounted to $40000. What will be the Schedule Variance?
Question 3
In a project to develop a new AI algorithm, the Planned Value (PV) is $100,000, and the Earned Value (EV) is $85,000. What is the Schedule Variance (SV)?