To-Complete Performance Index (TCPI)

5 minutes 5 Questions

To-Complete Performance Index (TCPI) is a projection of the anticipated performance required to achieve a goal. The TCPI can forecast how much efficiency must be achieved on the remaining work to meet a financial commitment. In essence, this metric tells us the cost performance index (CPI) that we …

Test mode:
CAPM - To-Complete Performance Index (TCPI) Example Questions

Test your knowledge of To-Complete Performance Index (TCPI)

Question 1

You are overseeing a construction project and the current AC stands at $140,000 and EV is $150,000. Assuming the cost baseline (BAC) is $500,000, how would you compute the To-Complete Performance Index (TCPI)?

Question 2

In a software implementation project, the actual cost (AC) currently stands at $400,000, the earned value (EV) stands at $380,000, and the planned value (PV) is $375,000. If there is an increase in project budget from $600,000 to $700,000, what will be the new To-Complete Performance Index (TCPI)?

Question 3

The To-Complete Performance Index (TCPI) is calculated as (BAC - EV) / (BAC - ________)

More To-Complete Performance Index (TCPI) questions
32 questions (total)