Bottom-Up Estimating
As the name implies, bottom-up estimating starts at the lowest level of the Work Breakdown Structure (WBS) and moves upwards to calculate the total estimate. This method gives a detailed and accurate estimate because it identifies costs at the task level. Though time-consuming and resource-intensiv…
CAPM - Bottom-Up Estimating Example Questions
Test your knowledge of Bottom-Up Estimating
Question 1
In a large-scale software project, different sub-teams have provided detailed time estimates for their respective parts. What should you do to estimate the project timeline using the bottom-up estimating method?
Question 2
A construction project is divided into several subprojects, each managed by a different contractor. The project manager has received detailed cost estimates from each contractor for their respective work packages. To determine the total project budget, the project manager should:
Question 3
A project manager is overseeing a software development project. The individual teams have submitted their estimates for their tasks. Which method would be the most appropriate for determining the overall estimate for the entire project?