Parametric Estimating
Parametric estimating involves using statistical modeling to make predictions. In this method, characteristics of the project (parameters) are represented in a mathematical model to predict project costs, resources, duration etc. The accuracy of the model depends on the quality and relevance of the data used. This method works best when the project parameters are quantifiable and can be reliably forecasted through the model. For instance, cost per square foot to build a commercial building.
Guide: Parametric Estimating in CAPM Estimation Techniques
Parametric Estimating:
Parametric Estimating is a technique used in the Cost Estimating and Assessment Guide to predict a project’s cost and duration through statistical modeling. By linking various project parameters to the cost and duration, one can quickly gauge the impact of change in any parameter on the project’s outcome.
Importance:
Parametric estimation plays a critical role in project management and cost estimation as it helps in predicting the cost and timeframe in a statistically significant manner. It also accounts for risk and uncertainty, thereby providing a more accurate and reliable estimate.
How It Works:
Parametric estimating works by establishing a statistical relationship between historical data and other variables (or parameters). For instance, you might calculate the cost of painting a room by determining the cost per square foot and the size of the room.
Responses to Questions about Parametric Estimating in Exams:
When answering questions about parametric estimating in exams, ensure to first explain what the approach is and emphasize its importance in managerial decision-making. Then, detail how it works, being sure to include relevant examples to demonstrate your understanding.
Exam Tips:
1. Understand the basic formula used in parametric estimating and be ready to apply it in situational problems.
2. Look out for words like 'parameters', 'variables' or 'statistical relationship' in the exam question – these are clues that parametric estimating may be the answer.
3. Always clarify how the data used in the estimation is obtained and reference any assumptions made.
4. The best answers will not only identify the cost/duration of a project but also explain how changes in input parameters can affect the estimate.
CAPM - Estimation Techniques Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
A project manager is estimating the cost of a landscaping project. The project will cover 5000 square feet and with each square foot costing $2.5 as per past experience. There's also a 10% contingency budget expected. What's the total estimate using parametric estimating?
Question 2
You are tasked to estimate the cost of a window installation project. Each window costs $250 to install based on previous projects. 20 windows are to be installed and there's an expected 5% contingency cost. What is the best estimate using parametric estimating?
Question 3
A software company is estimating the time required for code review using parametric estimating. There are 10 modules and each module takes approximately 3 hours for review. Including a 10% contingency time for unplanned events, what would be the best estimate for the task?
Go Premium
Certified Associate in Project Management Preparation Package (2024)
- Earn 15 PDUs needed for your CAPM certification
- 4454 Superior-grade Certified Associate in Project Management practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless CAPM preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!