PERT Estimating
The Program Evaluation and Review Technique (PERT) is a statistical tool used in project management to represent tasks or activities and their relationships. A PERT estimate is calculated as (Optimistic + (4 X Most Likely) + Pessimistic) / 6. This technique is useful when activities do not follow t…
CAPM - PERT Estimating Example Questions
Test your knowledge of PERT Estimating
Question 1
You're managing a project with an optimistic time of 10 days, a pessimistic time of 20 days, and a most likely time of 15 days. How will you calculate the PERT estimate?
Question 2
You're leading a marketing campaign project. The optimistic time estimate is 4 weeks, pessimistic is 10 weeks and the most likely time is 5 weeks. What should be the PERT estimate?
Question 3
You are the project manager for a construction project. The optimistic time is 12 weeks, the pessimistic time is 20 weeks, and the most likely time is 16 weeks. What is the PERT estimate for this project?