PERT Estimating
The Program Evaluation and Review Technique (PERT) is a statistical tool used in project management to represent tasks or activities and their relationships. A PERT estimate is calculated as (Optimistic + (4 X Most Likely) + Pessimistic) / 6. This technique is useful when activities do not follow t…
CAPM - PERT Estimating Example Questions
Test your knowledge of PERT Estimating
Question 1
You're managing a project with an optimistic time of 10 days, a pessimistic time of 20 days, and a most likely time of 15 days. How will you calculate the PERT estimate?
Question 2
You are the project manager for a construction project. The optimistic time is 12 weeks, the pessimistic time is 20 weeks, and the most likely time is 16 weeks. What is the PERT estimate for this project?
Question 3
You're leading a marketing campaign project. The optimistic time estimate is 4 weeks, pessimistic is 10 weeks and the most likely time is 5 weeks. What should be the PERT estimate?