Three-Point Estimating
Three-point estimating is a technique that uses statistical analysis to arrive at a project estimate. It uses three estimates to define an approximate range for an activity’s cost: the most optimistic cost (best-case scenario), the most pessimistic cost (worst-case scenario) and a most likely cost …
CAPM - Three-Point Estimating Example Questions
Test your knowledge of Three-Point Estimating
Question 1
The task of designing a new software architecture has optimistic estimate of 10 hours, most likely of 14 hours, and pessimistic of 25 hours. The client is asking for the expected task duration. Which Three-Point Estimating value should you provide?
Question 2
You are managing a software development project. For a particular task, the optimistic time estimate is 4 days, the most likely estimate is 6 days, and the pessimistic time estimate is 10 days. You are asked to evaluate the estimate having the highest possibility. Which answer should you choose by applying Three-Point Estimating?
Question 3
In a software development project, the development team estimates a critical feature to take optimistically 2 weeks, most likely 3 weeks, and pessimistically 5 weeks. The project manager needs to provide an estimate to the stakeholders that balances the potential variability in the estimate. Using the Three-Point Estimating technique, what would be the most appropriate estimate to provide?