Baseline Schedule

5 minutes 5 Questions

A Baseline Schedule is a fixed project schedule. It is the standard against which project performance is measured. The project schedule could change as the project progresses; however, the Baseline Schedule should only be modified if there is an approved change in scope, deliverables, or timeline. …

Test mode:
CAPM - Baseline Schedule Example Questions

Test your knowledge of Baseline Schedule

Question 1

During your project execution, you discover that the actual progress significantly differs from the baseline schedule. What is the most appropriate action to take?

Question 2

At the beginning of your project, you have established a baseline schedule. During a project status review meeting, a key stakeholder asks you to compress the schedule to meet an earlier delivery date. What is the most appropriate action to take as a project manager?

Question 3

Your project is progressing well, but you notice that actual resource usage is consistently lower than what was planned in the baseline schedule. What should you do?

More Baseline Schedule questions
12 questions (total)