Baseline Schedule
A Baseline Schedule is a fixed project schedule. It is the standard against which project performance is measured. The project schedule could change as the project progresses; however, the Baseline Schedule should only be modified if there is an approved change in scope, deliverables, or timeline. …
CAPM - Baseline Schedule Example Questions
Test your knowledge of Baseline Schedule
Question 1
During your project execution, you discover that the actual progress significantly differs from the baseline schedule. What is the most appropriate action to take?
Question 2
Your project is progressing well, but you notice that actual resource usage is consistently lower than what was planned in the baseline schedule. What should you do?
Question 3
At the beginning of your project, you have established a baseline schedule. During a project status review meeting, a key stakeholder asks you to compress the schedule to meet an earlier delivery date. What is the most appropriate action to take as a project manager?