Project Scope
Project scope refers to the detailed set of deliverables or features of a project. These deliverables are derived from a project's requirements. Project Scope is the common understanding among stakeholders about what goes into a project and what factors define its success. A project’s scope influences project planning in every way and once it’s defined, project managers plan the project path, schedule, and budget.
Guide: Understanding and Answering Questions on Project Scope
What is Project Scope?
Project Scope refers to the comprehensive list of deliverables, tasks, deadlines, and costs associated in a particular project. It is the backbone of every project as it defines what work is required and the timeline for its completion.
Why is it important?
Clearly defining the project scope prevents the occurrence of 'Scope Creep', a situation where additional tasks or requirements are added without revising the existing project plan. Mismanaged Scope Creep can result in cost overruns, missed deadlines, and project failure.
How does it work?
Project Scope works by following these steps: 1) Requirement Collection: Gathering information from clients and stakeholders. 2) Defining Scope: Creating a detailed project scope statement. 3) WBS Creation: Developing a Work Breakdown Structure to break down the tasks. 4) Validation: Getting approval of the scope from stakeholders.
Exam Tips: Answering Questions on Project Scope
1. Understand the concept thoroughly. Be able to define Project Scope, its importance, and its workings.
2. Use real-life examples to support your answers. This shows your practical understanding of the concept.
3. In case study questions, first identify the scope and then analyze how deviation from this leads to 'Scope Creep' .
4. Always refer to the steps of working with Project Scope while answering 'how to' questions.
CAPM - Project Scope Creep Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
Which of the following describes the approved version of the scope statement, work breakdown structure (WBS), and its associated WBS dictionary that is used as a basis for comparison throughout the project?
Question 2
During a project, the team discovers a significant opportunity to enhance the product's functionality. This enhancement was not part of the original scope. What is the most appropriate action for the project manager?
Question 3
During a project, you notice that team members are frequently adding small features that were not originally planned. This is causing the project to gradually expand beyond its initial boundaries. What is this phenomenon called?
Go Premium
Certified Associate in Project Management Preparation Package (2024)
- Earn 15 PDUs needed for your CAPM certification
- 4454 Superior-grade Certified Associate in Project Management practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless CAPM preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!