Variance Analysis
Variance Analysis in the context of Project Scope Management involves the process of quantitatively and qualitatively assessing the degree of difference between planned and actual project performance. This methodology enables the project management team to evaluate the overall impact of project ris…
CAPM - Variance Analysis Example Questions
Test your knowledge of Variance Analysis
Question 1
During a routine meeting to assess the software development project, the planned value was shared as $30,000. However, there was an actual cost amounting to $50,000 while the earned value was at $40,000. What does this signify in regard to project progress?
Question 2
When comparing actual cost with the earned value (EV) during a project, the result is showing a ______ variance.
Question 3
Alan, a project manager, realizes that the planned value of a certain project is $40,000, the actual cost is $50,000 and the earned value is $45,000. What could be the best step for Alan to take?