Controlling Schedule

5 minutes 5 Questions

Controlling schedule involves monitoring the status of project activities, updating project progress and managing changes to the schedule baseline. The aim is to ensure that the project remains on track and is delivered on time. Failure in schedule control can lead to project delays, cost overruns,…

Test mode:
CAPM - Controlling Schedule Example Questions

Test your knowledge of Controlling Schedule

Question 1

In reviewing your project's schedule, you observe that the float for several activities is becoming increasingly negative, indicative of potential delays. What should be your initial action to control the schedule?

Question 2

Critical path of your project shows a negative total float. What does this mean?

Question 3

The CPI of your project is currently at 1.3, but the project is still under schedule stress, with SPI at 0.8. What would your best course of action be?

More Controlling Schedule questions
12 questions (total)