Start practice test
Controlling Schedule - CAPM Project Time Management

What it is:
Controlling Schedule is a process in Project Time Management that monitors the status of the project activities to update project progress and manage changes to the schedule baseline.

Importance:
Controlling Schedule is critical as it ensures the project remains on track, highlights any deviations early on and ensures that corrective actions are taken in a timely manner to prevent delays.

How it works:
It involves measuring the actual project performance against the planned schedule, determining if any corrective or preventive actions are necessary and managing any changes required.

Exam Tips - Answering Questions on Controlling Schedule:
1. Understand the concept: Ensure you understand the basics of schedule control, and how it fits into the broader Project Time Management framework.
2. Understand the tools and techniques: Be familiar with schedule control tools like Gantt charts and Critical Path Method.
3. Practice: The more practice questions you solve, the better understanding you will have of how to apply the concept in a practical scenario.
4. Focus on change management: A lot of questions will revolve around managing changes within schedule control, so focus on that aspect.

Go Premium

Certified Associate in Project Management Preparation Package (2024)

  • Earn 15 PDUs needed for your CAPM certification
  • 6432 Superior-grade Certified Associate in Project Management practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CAPM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses
Controlling Schedule practice test

Controlling schedule involves monitoring the status of project activities, updating project progress and managing changes to the schedule baseline. The aim is to ensure that the project remains on track and is delivered on time. Failure in schedule control can lead to project delays, cost overruns, and unmet objectives. To control the schedule effectively, the project manager must use project management software, apply a performance review, and use project forecasting methods, among others.

Time: 5 minutes   Questions: 5

Test mode:

Practice more Controlling Schedule questions

More Controlling Schedule questions
8 questions (total)
Go Premium

Certified Associate in Project Management Preparation Package (2024)

  • Earn 15 PDUs needed for your CAPM certification
  • 6432 Superior-grade Certified Associate in Project Management practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CAPM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses