CAPM - Project Time Management - Critical Chain Project Management
Expert
1/5
Your project has five interconnected tasks in the critical chain, each with some buffer time. During execution, the first three tasks consume all their buffer time but the fourth task is completed well within time, freeing up some buffer time. What should you do with this freed up buffer?
a.
Ignore it as it is extra and not required.
b.
Keep the buffer time for the final task.
c.
Distribute the freed up buffer equally to all tasks.
d.
Use the buffer to start a new task.