CAPM - Project Time Management - Critical Chain Project Management
Expert
1/5
Your project has five interconnected tasks in the critical chain, each with some buffer time. During execution, the first three tasks consume all their buffer time but the fourth task is completed well within time, freeing up some buffer time. What should you do with this freed up buffer?