Estimating Activity Resources
Estimating activity resources means determining what resources are required (materials, people, equipment, etc.) and in what quantities for each activity. This process is crucial as resources often have cost implications (ownership cost, rental or usage fee, etc.) and availability constraints. Tech…
CAPM - Estimating Activity Resources Example Questions
Test your knowledge of Estimating Activity Resources
Question 1
As a project manager, you identify the need for a specialized consultant for a key project task. The consultant is currently available only at a significantly higher rate than budgeted. What should be your next step?
Question 2
You are the project manager of a team developing a new software. While discussing the project with the team, you realize that the complexity of a task has been underestimated and requires more resources. What is your next course of action?
Question 3
You are managing a construction project when you realize the need for an additional electrician due to the complexity of the wiring requirements. Your current team does not have this level of expertise. What is the most appropriate step to take?