PERT Analysis

5 minutes 5 Questions

Program Evaluation and Review Technique, commonly known as PERT, is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. PERT helps to identify the minimum time for completing a project along with the potential …

Test mode:
CAPM - PERT Analysis Example Questions

Test your knowledge of PERT Analysis

Question 1

Question: Jack is using PERT Analysis for his software project involving various complex tasks. For task X, the optimistic time is 5 days, the pessimistic time is 20 days, and the most likely time is 10 days. What is the variance for this task?

Question 2

Question: Peter is managing a project with a tight budget. He has completed a PERT analysis and calculated the standard deviation for each activity. How can he utilize this information?

Question 3

Anna is managing a digital transformation project. She decides to use the PERT analysis method for task Z, with a most likely time of 15 days, an optimistic time of 10 days, and a pessimistic time of 25 days. What would be the expected time for task Z?

More PERT Analysis questions
21 questions (total)