Work Breakdown Structure (WBS) - Complete Guide for CompTIA Project+
What is a Work Breakdown Structure (WBS)?
A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project by breaking it down into smaller, more manageable components called work packages.
Why is WBS Important?
The WBS is considered one of the most critical project management tools for several reasons:
• Scope Definition: It provides a clear and complete picture of all work required to complete the project
• Cost Estimation: Work packages allow for accurate cost estimates at the lowest level
• Schedule Development: Activities can be identified and sequenced based on work packages
• Resource Allocation: Teams can be assigned to specific work packages
• Risk Identification: Breaking down work helps identify potential risks at each level
• Progress Tracking: Provides a framework for measuring project performance
• Communication: Creates a common understanding of project scope among stakeholders
How Does a WBS Work?
The WBS follows a top-down approach using decomposition:
Level 1: Project Name (the entire project)
Level 2: Major Deliverables or Phases
Level 3: Sub-deliverables
Level 4: Work Packages (lowest level of the WBS)
The decomposition continues until work packages are small enough to be:
• Estimated accurately
• Assigned to a single person or team
• Completed within a reasonable timeframe
• Measured and controlled
Key WBS Components:
• WBS Dictionary: A document that provides detailed information about each WBS element, including descriptions, assumptions, constraints, and acceptance criteria
• Work Package: The lowest level of the WBS where cost and duration can be reliably estimated
• Control Account: A management control point where scope, budget, and schedule are integrated
• Planning Package: A WBS component below the control account with known work content but no detailed schedule activities
The 100% Rule:
The WBS must capture 100% of the work defined in the project scope. This means:
• All deliverables must be included
• No work should exist outside the WBS
• Each level must represent 100% of the work in the parent level
WBS Formats:
• Hierarchical/Organizational Chart: Visual tree structure format
• Indented Outline: Text-based list with numbered hierarchy
• Tabular Format: Spreadsheet-style presentation
Exam Tips: Answering Questions on Work Breakdown Structure (WBS)1. Remember Key Definitions:• WBS is a
deliverable-oriented hierarchical decomposition
• It defines
scope, not schedule or activities
• Work packages are the
lowest level of the WBS
2. Know What WBS Is NOT:• It is not a list of activities or tasks
• It is not an organizational chart of people
• It is not a project schedule
3. Common Exam Scenarios:• Questions about scope creep often relate to items being added that are not in the WBS
• Cost and schedule estimating questions reference work packages
• Questions about deliverables connect to WBS components
4. Associate WBS with These Processes:• Create WBS is part of
Scope Management• The WBS is created after the scope statement is defined
• It serves as input to cost estimating and schedule development
5. Watch for Trick Questions:• If a question asks about the lowest level where estimates occur, the answer is
work package• If asked about documenting WBS element details, the answer is
WBS Dictionary• The 100% rule ensures all project work is captured
6. Practice Recognition:• Recognize that WBS focuses on
what will be delivered
• Activities and tasks describe
how work will be done and come later in planning