Burn-Down Chart

5 minutes 5 Questions

A Burn-down Chart is a graphical representation of work left to do versus time in Scrum. The outstanding work (or backlog) is typically on the vertical axis, with time along the horizontal. Burn-down Charts are a run chart of outstanding work and are useful for predicting when all of the work for a sprint or release will be completed. It provides the team with a graphical view of how quickly they are working through the Customer's User Stories, and shows how much work is left to be done.

Guide on Burn-Down Chart

What is a Burn-Down Chart?
A burn-down chart is a graphical representation utilized in Scrum Project Management to portray the work left to do versus time.

Importance of a Burn-Down Chart
The burn-down chart is crucial as it visualizes the progress of the project and shows the total work remaining. It allows for better decision-making, helps to manage expectations, and provides a platform for communication within the team and with stakeholders.

How it Works:
The x-axis represents time, and the y-axis represents the amount of work. The chart starts with the most work at the beginning, and ideally it burns down to zero by the end of the project. Any deviations from the ideal line show whether the project is ahead or behind schedule.

Exam Tips: Answering Questions on Burn-Down Chart
1. Understand the concept and purpose of a burn-down chart.
2. Be able to interpret a burn-down chart.
3. Familiarize yourself with the terms involved.
4. Practice scenarios where you have to calculate remaining work based on a given burn-down chart.
5. Understand how changes in project variables are reflected in the chart.

Test mode:
CSM - Basic Scrum Concepts Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

The team managed to complete all tasks before the end of the sprint as shown by the burn-down chart. Still, the product owner is unhappy. As a ScrumMaster, what could be a possible explanation?

Question 2

You notice at the middle of the sprint, the burn-down chart shows the team is ahead of schedule, but at the end of the sprint, the work completed is below the ideal burn down line. As a Scrum Master, what could be the best explanation?

Question 3

The burn-down chart shows that the team's progress is consistently exceeding the projected burn-down line. As a Scrum Master, what could be a potential reason for this?

Go Premium

Certified ScrumMaster Preparation Package (2024)

  • 3861 Superior-grade Certified ScrumMaster practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CSM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Burn-Down Chart questions
17 questions (total)