CSM - Cross-functional Teams in Scrum - Clear and Shared Goals
Expert
1/5
During a Sprint, an external stakeholder demands urgent feature changes be included. How should the Scrum Master protect the team?
a.
Facilitate a discussion between the stakeholder and Product Owner to assess the request's impact on the Sprint Goal.
b.
Request the Product Owner to prioritize this demand in the Product Backlog for future Sprints.
c.
Advise the team to integrate the changes without affecting their current Sprint commitments.
d.
Instruct the team to focus on the current Sprint tasks and address the request in the next Sprint Planning.