Three Point Estimating

5 minutes 5 Questions

The Three Point Estimating technique is a statistical method which involves the use of multiple estimates to build a cost or schedule model for the project work. The team estimates with three points: Optimistic estimate (O), Most Likely (M), and Pessimistic (P). The project estimate can be calculated with a simple average or weighted average. This approach helps in getting more realistic estimates by reflecting the risk and uncertainty in the estimation process.

Guide to Three-Point Estimating

Importance:
Three-Point Estimating is crucial as it provides a realistic estimate by considering the optimistic, pessimistic, and realistic views rather than a single figure. It gives rich insights into project planning and risk assessment and helps manage stakeholder expectations.

Definition:
Essentially, Three-Point Estimating is a technique that uses three variables to analyze the time or resources required to complete a project task. The three variables are the Most Likely (M), Optimistic (O), and Pessimistic (P).

How it works:
Calculation of estimates in this technique involves two main formulae, Triangular Distribution and Beta Distribution. Triangular Distribution uses the formula: (O + M + P) / 3 and Beta Distribution, typically used in PERT method, uses the formula: (O + 4M + P) / 6.

Answering Exam Questions:
When answering questions on Three Point Estimating, read the question carefully and identify the values given for O, M, and P. Make sure you understand which formula to use for calculations. Always cross-verify your answers.

Exam Tips:
Remember to review Three-Point Estimating equations and principles. Understand the assumptions, contexts, and application of the technique. Understand when to apply Triangular or Beta Distribution. Remember that Three-Point Estimating takes into account uncertainty and risk, providing a more rounded estimate than traditional methods.

Test mode:
CSM - Estimation Techniques Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

You're observing a renovation project where the optimistic time to complete a job is 10 days, with most probable and pessimistic estimates being 15 days and 25 days respectively. What is the PERT estimate?

Question 2

You are managing a project in which a task has an optimistic estimate of 12 hours, a most likely estimate of 16 hours, and a pessimistic estimate of 24 hours. Using the Three-Point Estimating technique, what would be the estimate for this task if you prioritize avoiding delays?

Question 3

A graphic design task has an optimistic estimate of 30 minutes, a most likely estimate of 45 minutes, and a pessimistic estimate of 75 minutes. The design director expects a precise time schedule. Which Three-Point Estimating value best suits this case?

Go Premium

Certified ScrumMaster Preparation Package (2024)

  • 3861 Superior-grade Certified ScrumMaster practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CSM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Three Point Estimating questions
56 questions (total)