Three Point Estimating
The Three Point Estimating technique is a statistical method which involves the use of multiple estimates to build a cost or schedule model for the project work. The team estimates with three points: Optimistic estimate (O), Most Likely (M), and Pessimistic (P). The project estimate can be calculat…
CSM - Three Point Estimating Example Questions
Test your knowledge of Three Point Estimating
Question 1
You're observing a renovation project where the optimistic time to complete a job is 10 days, with most probable and pessimistic estimates being 15 days and 25 days respectively. What is the PERT estimate?
Question 2
You are managing a project in which a task has an optimistic estimate of 12 hours, a most likely estimate of 16 hours, and a pessimistic estimate of 24 hours. Using the Three-Point Estimating technique, what would be the estimate for this task if you prioritize avoiding delays?
Question 3
A graphic design task has an optimistic estimate of 30 minutes, a most likely estimate of 45 minutes, and a pessimistic estimate of 75 minutes. The design director expects a precise time schedule. Which Three-Point Estimating value best suits this case?