In agile methodologies like Scrum, estimating and planning is not a one-time activity, but a continuous process. It involves forecasting the amount of work that can be done in each sprint and, subsequently, in each release. During release planning, the team makes an educated guess or estimates, bas…In agile methodologies like Scrum, estimating and planning is not a one-time activity, but a continuous process. It involves forecasting the amount of work that can be done in each sprint and, subsequently, in each release. During release planning, the team makes an educated guess or estimates, based on their capacity and the size and complexity of the user stories in the product backlog. The outcome of this planning and estimating process significantly influences the release plan.
Guide and Exam Tips: Agile Estimating and Planning
What is Agile Estimating and Planning? Agile Estimating and Planning is a vital concept in the Agile project management framework that drives its efficiency. It involves forecasting the amount of work that can be accomplished in a sprint or iteration by the development team. Why is it important? This practice is crucial as it aids in delivering working software incrementally, responding to changes, meeting customer needs promptly and reduces the risk related to project development. How does it work? Agile Estimating and Planning involves breaking down a project into smaller tasks or user stories. Several estimation techniques are used, including t-shirt sizes, story points, and ideal days. All team members participate in this process to ensure a comprehensive estimate. Planning Poker is one commonly used method for fast and accurate estimation. After estimating, planning involves deciding which user stories will be completed for each iteration or sprint based on their priority. This plan is iterative and adaptable to changes. Answering Questions on Agile Estimating and Planning in an Exam: 1. Understand the concept: Thorough conceptual understanding is crucial in answering questions. Make sure you understand how Agile Estimating and Planning works and why it is important. 2. Use concrete Examples: Questions are likely to be scenario-based. Use concrete examples in your responses to demonstrate your understanding. 3. Keep it concise: Your answers should be straight to the point, capturing the essence of the question. 4. Be familiar with agile software: Knowing agile software will help answer questions related to practical application. 5. Understand estimation techniques: Different estimation techniques can be suited to different projects or teams. Understanding the variety and their application is essential to answer any related questions.
CSM - Agile Estimating and Planning Example Questions
Test your knowledge of Agile Estimating and Planning
Question 1
The developer team came up with an estimate of 60 story points for a particular user story which is much higher than estimations of other stories. What should you do?
Question 2
During sprint planning, the development team estimates that they can complete 80 story points worth of work. However, the Product Owner insists on adding more user stories that would total 120 story points. What should the Scrum Master do in this situation?
Question 3
Your team has recently completed sprint planning for a new software development project. The estimated size of a user story is larger than what can be completed in a single sprint. What should you do?
🎓 Unlock Premium Access
Certified ScrumMaster + ALL Certifications
🎓 Access to ALL Certifications: Study for any certification on our platform with one subscription
3861 Superior-grade Certified ScrumMaster practice questions
Unlimited practice tests across all certifications
Detailed explanations for every question
CSM: 5 full exams plus all other certification exams
100% Satisfaction Guaranteed: Full refund if unsatisfied
Risk-Free: 7-day free trial with all premium features!