BurnDown Charts
BurnDown Charts provides a graphical representation of the work remaining versus time. This simple visualization tool allows the team to understand at a glance whether it is making progress towards finishing the work in the time available. It is essentially a run chart that shows how quickly the team is burning through its customer's user stories. It’s useful for predicting when work will be completed.
The BurnDown Chart: Guide & Exam Tips
A BurnDown Chart is an essential tool used in agile project management, particularly in Scrum and related methodologies.
It is a graphical representation of work left to do versus time. It's a powerful visual aid that shows the progress towards a goal, making it simple for teams and stakeholders to understand the work situation.
Why is it Important?
BurnDown Charts are important because they provide fast and simple comprehension of the project's progress and if the team is on track. They can display potential issues in advance, like if additional resources are needed to meet the deadline.
How it Works?
The chart consists of an X-axis (which represents time) and a Y-axis (representing the amount of work left). As tasks are completed, the line in the chart 'burns down' to zero.
Exam Tips: Answering Questions on BurnDown Charts
1. Understand the basics: Know how to read and interpret a BurnDown Chart.
2. Practical example: Be able to draw a basic BurnDown Chart and explain what it means.
3. Real-world application: Discuss how BurnDown Charts can aid in project management, highlighting their benefits and potential drawbacks.
4. Understand variations: Be aware of different types of BurnDown Charts and when each is used.
Always read the question carefully to understand what is asked, whether it's definition, interpretation, or practical application. And remember, examples can help illustrate your understanding.
CSM - Release Planning Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
In an ongoing sprint, the burn down chart shows a sudden rise, then a plateau. During reviews, you realize some additional tasks were reported, but haven't yet begun. How should you manage this?
Question 2
The Burn-Down chart for your current sprint appears to be a slight upward curve.This is the first time the team is ahead of schedule. How would you interpret and act on this?
Question 3
During a sprint, the team realizes that a significant number of tasks are not yet done. Your burn-down chart is not hitting the x-axis as anticipated. What could be an ideal step to take in this scenario?
Go Premium
Certified ScrumMaster Preparation Package (2024)
- 3861 Superior-grade Certified ScrumMaster practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless CSM preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!