In the context of a Release Burnup Chart, what does it indicate if the slope of the 'total work done' line sharply increases but the 'work remaining' line remains constant?
a.
The development team is facing challenges in completing tasks as planned.
b.
A reduction in the project's scope without impacting productivity.
c.
The team has added more features to the backlog, increasing scope.
d.
A surge in productivity with no change in project scope.