Some of the tasks in the sprint backlog turn out to be irrelevant for the sprint goal. What is the correct course of action?
a.
Replace the irrelevant tasks with new tasks without discussing with the Product Owner
b.
Remove the tasks without informing the Product Owner
c.
Remove the irrelevant tasks from the sprint backlog after confirming with the Product Owner
d.
Continue working on them as they are already in the sprint backlog