Register
4:59
Stop
CSM - Scrum Artifacts - Scrum Team
Beginner
1/5
In a situation where the Scrum Team faces frequent scope changes within a sprint, severely impacting their ability to deliver the committed items, what is the most effective course of action a ScrumMaster should take?
a.
Insist on strict adherence to the original Sprint Backlog to ensure the delivery of committed items before allowing any scope changes.
b.
Facilitate a session between the Product Owner and the team to discuss the impact of changes and renegotiate the Sprint Backlog as necessary.
c.
Encourage the team to work overtime to incorporate the changes without affecting the originally committed Sprint Backlog items.
d.
Suggest the Product Owner to reduce the number of items for future sprints to accommodate potential scope changes.
Beginner