CSM - Scrum Ceremonies - Scrum Sprint Planning
Master
1/5
If a team realizes halfway through the sprint planning that the original Sprint Goal is unachievable due to an unforeseen dependency, what should be the appropriate next step?
a.
Revise the Sprint Goal to reflect the new understanding.
b.
Keep the original Sprint Goal and adjust the workload accordingly.
c.
Cancel the sprint and start planning a new one.
d.
Prioritize the dependency and postpone the original Sprint Goal to the next sprint.
Master