CSM - Scrum in Different Industries - Scrum Events
Intermediate
1/5
What is the most appropriate way for a Scrum Master to address a consistent decline in the Development Team's velocity over several Sprints?
a.
Encourage the team to work longer hours and weekends to increase their velocity and meet the original estimates
b.
Facilitate a retrospective to identify and address potential impediments or process improvements
c.
Adjust the velocity calculations to show an artificial increase and maintain stakeholder confidence in the team's performance
d.
Report the decline in velocity to management and request additional resources to be added to the team
Intermediate