During a sprint planning meeting, your development team realizes they do not have the capacity to fulfill the product owner’s expectations for the upcoming sprint. How should you proceed?
a.
Shift some workload to the next sprint without discussing with the product owner.
b.
Proceed with the initial plan, overtime might be needed.
c.
Re-negotiate the sprint backlog with the product owner based on realistic capacities.
d.
Cancel the sprint completely and start planning again.