Guide to Understanding and Answering Questions on Burndown Chart

What is a Burndown Chart?
A burndown chart is a graphical representation of work left to do versus time. It is one of the key tools used in Scrum project management to track progress and estimate work completion date. The Y-axis represents the amount of work remaining and the X-axis represents time.

Why is it important?
A burndown chart is essential for predicting if the project remains on track to complete in projected time. It serves as a visual aid for tracking progress, identifying potential problems early, and managing scope and timelines effectively.

How does it work?
The lines in a burndown chart indicate the actual and projected amount of work to be done. If the actual work line is above the ideal line, you're behind schedule; if it's below, you're ahead.

Exam Tips: Answering Questions on Burndown Chart
1. Understand the basic concept and its purpose in project management.
2. Be able to interpret a burndown chart and understand what it signifies regarding project progress.
3. Remember that the chart burndowns only if work gets completed and not just based on time passage.
4. Practice drawing and interpreting burndown charts with different project scenarios.
5. Be clear that burndown charts are for tracking progress and spotting trends, not for detailed project scheduling or fault allocation.
6. In your answers, emphasize the visual and predictive power of burndown charts in Scrum Project Management.

Go Premium

Certified ScrumMaster Preparation Package (2024)

  • 5543 Superior-grade Certified ScrumMaster practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CSM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses
Burndown Chart practice test

The Burndown Chart is a visual representation of the work remaining in a sprint versus time. It is one of the most common techniques used in Scrum to track a team’s progress. The X-axis represents time, and the Y-axis represents work. At the start of the sprint, the total amount of work to be done is plotted, and as tasks are completed, the plot 'burns down' to zero. This chart helps a scrum team to anticipate problems and take necessary actions, manage efficiently their pace and expectation from stakeholders and client side.

Time: 5 minutes   Questions: 5

Test mode:

Practice more Burndown Chart questions

More Burndown Chart questions
30 questions (total)
Go Premium

Certified ScrumMaster Preparation Package (2024)

  • 5543 Superior-grade Certified ScrumMaster practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CSM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses