CSM - Scrum Tools and Techniques - Velocity
Intermediate
1/5
Team Yankee predicts their velocity will vary due to a team member’s vacation. What actions should the ScrumMaster take?
a.
Recruit a new member into the team to cover for the vacationing individual.
b.
Insist on the team member working during vacation to maintain velocity.
c.
Ignore the potential impact on velocity and continue as usual.
d.
Tag the story points completed by the individual and take note of potential velocity change while they're on vacation.
Intermediate