CSM - Scrum Values and Principles - Incremental Delivery
Beginner
1/47
As a Certified ScrumMaster, your team is on the verge of completing the second increment of a four-increment project. The customer approaches and wants to shift the focus to a new set of functionalities. How do you respond?
a.
Ignore the customer's request as the team is already burdened with planned functionalities.
b.
Immediately shift focus to the new functionalities, disregarding the planned features.
c.
Deny the change since it might disrupt the existing project plan.
d.
Discuss it with the team, re-plan remaining increments considering the new set of functionalities, while also maintaining a balance with planned features.
Beginner