CSM - Scrum Values and Principles - Incremental Delivery
Intermediate
1/5
When using The Bucket System, what should a ScrumMaster do if the team is consistently failing to complete items in the hot bucket?
a.
Escalate the issue to management and request additional resources or extended deadlines
b.
Collaborate with the team to identify and address any impediments or bottlenecks
c.
Encourage the team to work overtime or on weekends to ensure all hot bucket items are completed within the sprint
d.
Automatically move incomplete items back to the warm bucket to reduce pressure on the team
Intermediate