CSM - Sprint Planning and Execution - Sprint Execution
Beginner
1/7
Due to unexpected complexity, the team has realized halfway through the sprint that they cannot deliver all features by the end of the sprint. What is the best course of action?
a.
Continue with the existing sprint backlog and try to rush the work.
b.
Stop the ongoing sprint and start a new one.
c.
Discuss the situation with the Product Owner and adjust the Sprint Backlog and objectives accordingly.
d.
Ask for additional workforce to help complete the work.