Register
11:59
Stop
PMI-ACP - Agile Estimation Techniques - Large, Uncertain, Small
Expert
1/12
You are working on a large project with a small team that faces high-level uncertainties. The client has a flexible delivery time. Which is the most effective way to mitigate risk in this scenario?
a.
Breaking the tasks into manageable chunks and prioritizing them based on risk and value to the project.
b.
Limiting communication with the client to prevent further uncertainties.
c.
Adding more people to your team to share the workload.
d.
Focusing on the easier tasks first to have quick wins.
Expert