Proportional Estimating

5 minutes 5 Questions

Proportional estimating is an Agile estimation technique which compares features or functionalities of a project in terms of size or complexity, to provide the relative estimate. Often this technique can be faster than other methods as it requires less granularity. However, it also assumes that the…

Test mode:
PMI-ACP - Proportional Estimating Example Questions

Test your knowledge of Proportional Estimating

Question 1

You are functioning as a Scrum Master. A task is estimated to require 18 hours. A different task perceived to be 35% less complex is added. Deploying Proportional Estimating, what should be the estimation for the newly added task?

Question 2

As a Scrum Master, you've estimated a task to take 5 hours to complete. A new task that's half less complex is added to the backlog. Using Proportional Estimating, how long do you predict the new task will take?

Question 3

As the product owner in a project, a task estimated to take 8 days is added to the backlog. Another task is believed to be 50% less complex than the previous task. Using Proportional Estimating, what's your estimate on how long the new task will take?