PMI-ACP - Agile Principles and Mindsets - Embrace Change
Intermediate
1/5
In the midst of a project, your client demands to add a new feature that was not included originally. What is your best approach?
a.
Inform the client that changes can't be made once a project has started.
b.
Charge extra fees without explaining why.
c.
Welcome the new change and make necessary adaptations to accommodate this change.
d.
Ignore the client's request and continue with the initial plan.