PMI-ACP - Agile Risk Management - Agile Risk-based Prioritization
Expert
1/9
In your Agile team, a new risk has emerged during the ongoing sprint that can affect the completion date. According to Agile risk-based prioritization, how should the team approach this problem?
a.
Request more resources from the Product Owner
b.
Re-evaluate the sprint backlog and prioritize the risk
c.
Work extra hours to address the risk
d.
Ignore the risk until the next sprint