PMI-ACP - Agile Risk Management - Risk Ownership
Advanced
1/5
As a Scrum Master, you discover that some newly identified risks have not been assigned owners. The project team members are overloaded and do not have the capacity to take on additional risk ownership. What should be your course of action in this situation?