Burndown Charts
Burndown Charts provide a graphical representation of work left to do versus time. The chart is updated daily and provides a simple view of the project's progress and projections. It can consistently communicate the team's status to stakeholders and within the team. Burndown Charts are effective to…
PMI-ACP - Burndown Charts Example Questions
Test your knowledge of Burndown Charts
Question 1
Halfway through the sprint, your team's Burndown Chart is showing an uptrend despite no new work being added. The team provides daily updates on work completed. What could be a plausible explanation?
Question 2
Your team's Burndown Chart displays a horizontal trend with a sudden drop in the end. How might you interpret this pattern?
Question 3
The Burndown Chart depicts oscillations above and below the ideal trend line. What could explain such a pattern?