Register
46:00
Stop
PMI-PBA - Project Management Basics for Business Analysts - Project Integration Management for Business Analysts
Expert
1/46
During a project retrospective meeting, several team members express concerns about varying interpretations of work processes across departments. Which Project Integration Management component would best address this situation?
a.
Organizational Process Assets review and update
b.
Implementation of a comprehensive change management system with extensive documentation and approval workflows
c.
Development of an integrated performance measurement baseline
d.
Creation of a detailed stakeholder engagement matrix and communication plan
Expert