PMI-PBA - Requirements Planning and Management - Requirements Verification and Validation Planning
Expert
1/5
Which metric is most valuable when evaluating the effectiveness of requirements verification and validation activities?
a.
Total count of requirements that passed initial stakeholder reviews and technical assessments
b.
Rate of requirements acceptance by stakeholders during formal review sessions
c.
Number of defects found during early testing phases
d.
Percentage of requirements that align with organizational strategic objectives and business goals
Expert