What is the most effective sequence for distributing peer review findings to stakeholders in a business analysis project?
a.
Compile findings, prioritize issues, send summary report, schedule follow-up
b.
Create presentation slides, deliver findings in person, collect signatures, distribute meeting minutes
c.
Send individual feedback forms, wait for responses, compile data, present to management
d.
Schedule meeting, collect feedback, document issues, send detailed technical analysis with complete code references