PMI-RMP - Communication and Risk Reporting - Risk Communication Roles and Responsibilities
Expert
1/12
During risk identification workshops, which role should be assigned to consolidate and synthesize diverse risk perspectives into coherent risk statements?
a.
The Risk Management Team collectively votes on the most appropriate way to phrase each risk
b.
Subject Matter Experts evaluate technical aspects and provide recommended risk statement language
c.
The Project Sponsor reviews all risk inputs and makes final determinations on risk statement wording
d.
The Risk Facilitator coordinates input from stakeholders and formats risk descriptions