PMI-RMP - Communication and Risk Reporting - Risk Escalation and Reporting Hierarchy
Expert
1/12
In a PMI-RMP context, what is the most effective way to structure risk escalation communications between multiple project stakeholders?
a.
Implement a centralized risk management system where all stakeholders receive automated notifications for any risk occurrence
b.
Create detailed risk reports that document all project issues and distribute them to every stakeholder on a monthly basis
c.
Establish clear severity thresholds and corresponding communication paths for each stakeholder level
d.
Develop comprehensive risk matrices that outline potential scenarios and mandatory response actions for each project phase