In your project, a team member develops a rapid solution to handle an unexpected issue. Which characteristic best defines this solution as a workaround?
a.
It is a solution that uses existing management reserve allocations
b.
It represents a pre-approved response strategy from the risk register
c.
It is a proactive measure developed during initial risk planning sessions
d.
It is an unplanned response to an identified risk that has occurred